FLOW • HEAD • POWER • NPSH
Boiler Feed Pump Calculator
Build a transparent preliminary pump duty from steam production, feedwater conditions, system pressure and piping losses.
STEP-BY-STEP METHOD
Boiler feed pump flow calculation
The pump must replace steam leaving the boiler plus continuous blowdown. The calculator then applies the entered design margin and adjusts for the percentage of time the pump is available to run.
Blowdown based on steam
Base feed = steam × (1 + blowdown %)Blowdown based on feedwater
Base feed = steam ÷ (1 − blowdown %)Design mass flow
Base feed × flow margin ÷ duty cycleDesign volume flow
Mass flow ÷ water densityA continuously modulating pump can use a 100% duty cycle. An intermittent on/off pump may need a substantially greater capacity because the required hourly water must be delivered during a shorter running period.
Boiler feed pump head calculation
Pressure difference is converted to metres of the entered-temperature water using:
Pressure head = ΔP ÷ (ρ × g)
Static elevation rise and pipe/fitting loss are added to pressure head. The selected head margin is applied last:
Design head = (pressure head + static lift + friction head) × (1 + head margin)
The correct pump is selected at the intersection of the required design flow and head—not from shut-off pressure alone.
Pump and motor power methodology
Hydraulic power
Ph = ρ × g × Q × HPump shaft power
Pshaft = Ph ÷ ηpumpMotor input
Pinput = Pshaft ÷ ηmotorThe result is not a nameplate recommendation. Final motor sizing must use the complete pump power curve and account for service factor, voltage, starting method, ambient temperature, enclosure, applicable codes and any operating case that can overload the driver.
NPSH available and hot feedwater
Hot water has a higher vapor pressure, reducing the pressure margin before flashing. The optional calculation uses:
NPSHa = (surface absolute pressure − vapor pressure) ÷ (ρg) + liquid level − suction loss
NPSHa belongs to the system. NPSHr belongs to a specific pump and changes with flow and speed. Obtain NPSHr from the manufacturer’s curve, then apply the additional margin required by the project specification or governing standard. A simple NPSHa greater than NPSHr comparison is not, by itself, a complete cavitation assessment.
Water density and saturation vapor pressure are estimated by interpolation from temperature property data aligned with IAPWS water/steam formulations. Confirm properties separately for final design, especially for pressurised deaerators and very hot feedwater.
Worked boiler feed pump example
The result uses an interpolated water density of 965.1 kg/m³ at 90°C.
Use the “Load example” button to reproduce the calculation and review each intermediate value.
Engineering checks before pump selection
Check minimum, normal and maximum boiler loads against the pump curve and minimum continuous stable flow.
Verify NPSH margin, tank pressure and level, suction-pipe velocity, strainers and hot-water flashing risk.
Confirm materials, seals, bearings, temperature/pressure ratings, balance devices and required redundancy.
Review control-valve authority, recirculation, start-up, standby switchover, trips and boiler level-control response.
Technical references
Reference material: U.S. Department of Energy pump hydraulic-power definition, Spirax Sarco feedtank and cavitation guidance, Xylem NPSH guidance, and the IAPWS industrial water and steam property formulation.
Boiler feed pump calculator FAQs
What does this boiler feed pump calculator calculate?
It estimates design feedwater mass and volume flow, differential pressure, total dynamic head, hydraulic power, pump shaft power, motor input power and optional net positive suction head available.
How is boiler feed pump flow calculated?
Maximum steam production is increased for blowdown, the selected flow margin and any reduction in available pumping duty cycle. Water density at the entered feedwater temperature converts mass flow to volume flow.
Should blowdown percentage be based on steam or feedwater?
Both conventions are used. Select the basis matching the source data. If blowdown is a percentage of steam, feedwater equals steam multiplied by one plus the percentage. If it is a percentage of feedwater, feedwater equals steam divided by one minus the percentage.
How is boiler feed pump head calculated?
Pressure head is calculated from boiler pressure plus valve allowance minus feedtank pressure. Static elevation rise, piping loss and the selected head margin are then included.
Why is feedwater temperature required?
Temperature changes water density, volume flow, pressure-to-head conversion and vapor pressure. Hot feedwater also reduces the suction margin available before flashing and cavitation.
What is NPSH available?
NPSHa is a property of the suction system. This calculator uses feedtank surface absolute pressure, water vapor pressure, liquid level above the pump and suction-line losses.
Where does NPSH required come from?
NPSHr is a characteristic of a specific pump at a specific flow and speed. Obtain it from the manufacturer’s pump curve and apply the margin required by the project specification or applicable standard.
Is calculated motor input the motor nameplate size?
No. It is the estimated electrical input at the calculated duty and entered efficiencies. Final motor selection must consider the full pump curve, service factor, starting method, voltage, ambient conditions and applicable codes.
Can this calculator select a boiler feed pump model?
No. It defines a preliminary duty point. A qualified engineer and the boiler and pump manufacturers must verify curves, materials, minimum flow, seals, temperature limits, NPSH margin, redundancy and transient conditions.
Are entered system values stored?
No. The calculations run locally in the browser, and the plugin does not submit or store entered plant data.